Case Study 03 · Heritage

Rewiring a Grade II Bath property without disturbing original features

A 4-bed terraced Georgian-conversion in Bath. Nine working days, conservation officer liaison, invisible cable routing, brass-finish accessory schedule, full RCBO board with AFDD on the bedroom circuit and a surge-protection device on the incomer.

By Dan Stevens, Director · DS Electrical · 4 May 2026
NAPIT
Approved 66245
CHAS
Accredited 158368
2391
City & Guilds
TrustMark
Government Endorsed
Part P
Building Regulations
BS 7671
18th Edition Compliant

Generic case study. We do not name the property, the address, or the owner — the value is the method, the cable strategy and the accessory schedule.

The brief

A Grade II listed Georgian-conversion property in central Bath, 4 bedrooms across three floors, with a basement kitchen and original features throughout: working sash windows, lath-and-plaster ceilings, the original staircase, panelled doors, picture rails, and a continuous run of original architrave the owner specifically did not want chasing into. The wiring was an aging mix of late-1970s rubber-sheathed and post-1990s twin-and-earth, with a wooden-back fuseboard in a basement cupboard. EICR had come back UNSATISFACTORY (multiple C2s) and the brief was a full rewire — without leaving a mark on anything original.

Conservation officer liaison

Listed-building consent isn't always required for a like-for-like internal rewire, but on a Grade II property it pays to assume it might be. We:

Approach detail covered in heritage installations.

Period brass lantern hanging in a stairwell of the heritage Bath property
Period brass lantern, stairwell. Wired through the original ceiling void with no surface conduit and no replastering.

Invisible cable routing strategy

The whole job lives or dies on the cable strategy. The principles were:

  1. Use existing voids first. Lift floorboards in the order they were originally laid (numbered with chalk, photographed, replaced sequentially). Run cables in joist drillings, not on top of joists, with grommets at every drilled hole.
  2. Drop, don't chase. Wherever possible, drop into the wall from the ceiling void above rather than chasing up from a socket position. The chase, if needed, is short and behind the skirting.
  3. Behind the skirting, not through it. Original skirting is removed carefully (not split), cables laid in the wall behind, skirting refitted with the original nails or matching cut nails.
  4. Reuse original switch and socket back-boxes wherever they're sound. New back-boxes only where the old ones were galvanised steel of unknown age.
  5. No surface conduit on principal elevations. Anywhere visible, the wiring is invisible.
Period wall sconce installed at picture-rail height in the principal bedroom
Wall sconce, principal bedroom. Wired from the ceiling void above, no chasing into the original lath-and-plaster.

Brass-finish accessory schedule

The visible kit was specified to match the period of the property, not bolted on as an afterthought. The accessory schedule was approved with the owner before any kit was ordered:

Heritage kitchen of the rewired Bath property post-completion
Basement kitchen, post-completion. Under-cabinet LED, RCBO-protected ring, dedicated radial for the range, all hidden behind the cabinetry.

Staged install over 2 weeks

The job was sequenced as 9 working days across 2 weeks, with the property occupied throughout (the owner moved between rooms as we worked):

  1. Day 1 — Strip-out, protection, photography. Original features dust-sheeted, floorboards numbered and lifted in the work zones, photographs of every original detail.
  2. Days 2–4 — First fix. All new cabling pulled through ceiling voids and joist drillings. Existing wiring left live in parallel where possible so the owner didn't lose lighting overnight.
  3. Day 5 — Board change. New consumer unit installed in basement cupboard (same location, replacement kit). Property on temporary supply for the day.
  4. Days 6–7 — Second fix. Brass accessories fitted, switches and sockets terminated, lighting hung.
  5. Day 8 — Test & cert. Full BS 7671 inspection-and-test, every circuit, every reading logged.
  6. Day 9 — Handover. Walk-through with the owner, every circuit demonstrated, paperwork issued.

The new board

ComponentSpec
Consumer unitMetal-clad 18-way, RCBO per circuit
Surge protectionType 2 SPD on the incoming
AFDDBedroom-circuit AFDD per BS 7671 sleeping-accommodation guidance
RCBOsType A, 30 mA, full per-circuit individual protection
Tails & bonding25 mm² tails, 10 mm² main protective bonding
EarthingVerified, labelled, photographs on file

BS 7671 cert + Part P

Handover paperwork:

Why this approach. A heritage property gets one chance at a rewire that doesn't damage it. Plan the cable routes before lifting a board, agree the accessory schedule before ordering kit, document everything before you change anything. The job takes longer in planning than it does on site — that's deliberate.

Also see: house rewires, heritage installations, heritage listed-building wiring guide.

About the figures. The property type (4-bed terraced Bath, Grade II Georgian conversion), duration (9 working days), and board specification (18-way RCBO with AFDD on bedroom circuit and Type 2 SPD) describe a representative reference job. Your heritage rewire will be priced on its own survey and approved with the conservation officer before any work starts. All prices on the DS Electrical website and in our quotes are subject to VAT at the current rate (20%). DS Electrical Installations (SW) Ltd is VAT-registered (GB 429 0409 05).

Heritage rewire on the cards?

Survey, conservation liaison, accessory schedule agreed before any kit is ordered. Bath, Wells and Mid Somerset only.

07889 334849
Get a Quote WhatsApp Heritage Installations
Call Dan — 07889 334849
Call Dan07889 334849 WhatsApp Email